Material availability check on in the kanban board for transfer jobs

One of the basic applications of kanbans is to replenish purchased material in kanban supermarkets in production. Replenishment is handled using a kanban transfer job on the kanban board for transfer jobs. The status of a kanban transfer job can be one of the following

  • Not planned
  • In Progress
  • Completed

A transfer job changes from status “Not planned” to “In Progress” when the user selects the Start button in the kanban board. The “In progress” status is useful when a transfer job will run for a long time. For short-termed transfer jobs where, for example, the material is stored close to the place of consumption, the “In progress” status can be skipped and instead be set directly to “Completed”. For the scenarios where the “In progress” status is used, we have identified the following two challenges

Challenge 1

A user can start a job, even though the required materials are not available, because inventory isn’t updated until the transfer job is completed (similar to posting an inventory transfer journal)

Scenario: A worker starts the transfer job without using the supply status, found in the picking list tab page, to check for on-hand inventory. When he arrives to the picking location to pick up the material, he discovers that the material is not available.

Challenge 2

The system does not allocate the materials to the job when it is started

Scenario: A worker starts the transfer job after using the supply status to verifying that material is on-hand. He walks over to the picking location, but the material is no longer available because it was picked for another job.

 

To prevent these situations from happening, we have introduced the following capabilities in CU7

  • The availability of materials is verified when a transfer job is started
  • The quantity of the materials required for a transfer job are reserved when a transfer job is started

If a worker tries to start a transfer job when the material is not available, the job cannot be started and go to status “In progress”. The worker will be notified that material in not on-hand in the messages section in the transfer board.


 
    
If the required quantity for the job is available, the system makes a physical reservation for the material. In that way it cannot be allocated to other jobs. One thing to note here is that the reservation is not canceled if the status of the transfer job is reverted from “In progress” to “Not planned.” The worker must cancel the reservation on the Reservation form, which is now available from the picking lines in the transfer board. The menu item to the On-hand form has also been made available there.

 

 

 


 

Now available: Cumulative Update 7, featuring the product change case management

With the recent release of Cumulative Update 7 for Microsoft Dynamics AX 2012 R2, the case management functionality of Microsoft Dynamics AX has been enhanced for documenting and releasing product changes to production.

Many manufacturing companies will welcome this simple built in possibility of creating product change cases to document component substitutions in bills of materials or formulas, or changes in the production route, and of being able to visualize the impact of such component changes.

The new product change functionality provides enhanced support for approval and activation of the changes to bills of materials, formulas and routes that are associated with a product change case, which reduces the effort needed for releasing product changes to planning and production. This new capability also offers a new opportunity to integrate changes from an external PLM solution into Microsoft Dynamics AX with the context of the PLM change order with enhanced support for validation, approval and activation in production.

The diagram below illustrates the overall product change process, and highlights those elements (with black outline) that are supported by the new product change features in Cumulative Update 7 for Microsoft Dynamics AX 2012 R2.

Meet me at Convergence EMEA 2013 at the Manufacturing booth if you would like to see the feature in action.

We will soon share more details about this new functionality in this blog.

 

 

Download it now!

Microsoft Dynamics AX 2012 R2 Cumulative Update 7 (KB2885603) – build #6.2.1000.4051